Section 20 legislation encourages fairness and transparency when selecting contractors for expensive works or long-term agreements. For RTM and RMC directors, getting the process right protects leaseholders and reduces the risk of disputes, delays, and unrecoverable costs.

In practice, Section 20 can feel confusing on first pass. This guide breaks down the key rules from the Landlord and Tenant Act 1985 into plain English, including timelines, notice requirements, and what to do when emergencies do not allow a full consultation.

TL;DR

  • Section 20 applies where any leaseholder would be required to contribute more than £250 for works, more than £100 per year under a long-term agreement, or when entering into a long-term agreement
  • Most consultations require 3 notices and take at least 2 months
  • Leaseholders must be given a real opportunity to comment and nominate contractors
  • You must obtain estimates correctly and justify your decision if not choosing the cheapest (and not nominated) contractor
  • If you get it wrong, contributions may be capped
  • In emergencies, works can proceed, but you may need to apply for dispensation

What we’ll cover

The basics – what you must know at a minimum:

  • When are Section 20 consultations necessary?
  • How many notices need to be sent?
  • How long does the process take?

The details – common FAQs:

  • How should Section 20 notices be sent to leaseholders?
  • What are the consequences if Section 20 is not followed correctly?
  • What if there’s an emergency and work needs to be expedited?
  • How can Flatwise help?

When is Section 20 required?

There are three scenarios where Section 20 is required and each follows their own process, known as a schedule:

1. Carrying out “qualifying works” (most common for RTMs and RMCs)

  • Works “qualify” if the contribution of any one leaseholder exceeds £250
  • This includes major works such as roof repairs, structural works, or external redecorations

2. Entering into a long-term agreement

  • A long-term agreement is a contract that lasts more than 12 months
  • Examples include cleaning contracts, gardening, or lift maintenance

3. Qualifying works under a long-term agreement

  • Works carried out under an existing long-term agreement
  • Consultation is required if the contribution from any leaseholder exceeds £100 per year

How long does the process take?

For qualifying works and long-term agreements, the process will typically take at least 2 months, as it involves:

  • A 30-day consultation period following the Notice of Intention
  • A further 30-day consultation period following the Statement of Estimates

In practice, the process often takes longer once time is allowed for preparing notices, obtaining estimates, and reviewing observations.

What do I need to do to follow the Section 20 schedules?

The schedules for “Carrying out qualifying works” and “Entering into a long-term agreement” both require three notices to be sent out:

  • Notice of Intention
  • Statement of Estimates
  • Notice of Reasons

1. Notice of Intention

This is the first step in the process.

You must include:

  • A description of the proposed works or services
  • The reasons why the works are necessary
  • An invitation for leaseholders to:
  • Submit written observations
  • Nominate contractors

Key points:

  • A consultation period of at least 30 days must be provided
  • All observations must be considered and responded to

2. Statement of Estimates (Notice of Estimates)

After the consultation period:

You must obtain a minimum of two estimates:

  • At least one estimate from a contractor wholly unconnected to the landlord
  • Estimates from any nominated contractors (where reasonably practicable)

The notice must include:

  • Either the estimates themselves or a summary of the estimates
  • Details of where and when the full estimates can be inspected
  • An invitation for further observations

Leaseholders must be given a reasonable opportunity to inspect the estimates.

Key points:

  • A further 30-day consultation period is required

3. Notice of Reasons

This notice is only required in specific circumstances.

You must issue a Notice of Reasons if:

  • You do not select the cheapest estimate, and
  • The chosen contractor was not nominated by a leaseholder

This notice must:

  • Be sent within 21 days of entering into the contract
  • Clearly explain why the contractor was chosen (e.g. quality, experience, programme of works)

Qualifying works under a long-term agreement

For works under an existing long-term agreement (where the agreement itself has already been subject to consultation), the process is simpler:

  • Only a Notice of Intention is required
  • A 30-day consultation period still applies
  • There is no requirement for a Statement of Estimates or Notice of Reasons

FAQs

How should Section 20 notices be sent to leaseholders (how must they be notified)?

At a minimum, notices must be served in accordance with the lease and statutory requirements.

This typically means:

  • By post to the leaseholder’s address, or
  • By hand delivery

Email can only be used if the leaseholder has formally agreed in writing to receive notices electronically.

In addition:

  • Notices must be in writing
  • They must contain all required statutory information
  • Leaseholders must be given a genuine opportunity to respond within the consultation periods

What are the consequences if Section 20 is not followed correctly?

If the process is not followed:

Contributions are capped at:

  • £250 per leaseholder for qualifying works
  • £100 per leaseholder per year for long-term agreements

You can apply to the First-tier Tribunal for dispensation, but:

  • This is not guaranteed
  • It can be time-consuming and costly

It’s an emergency and we can’t wait 2 months — what can we do?

This situation comes up more often than you might think.

In genuine emergencies (e.g. major leaks, structural risks, health and safety concerns), you may not have time to complete the full consultation process.

In these cases:

  • You can proceed with the works
  • But you should carry out as much consultation as reasonably possible in the circumstances

Afterwards, you may need to apply for dispensation from the consultation requirements.

This involves applying to the First-tier Tribunal under Section 20ZA of the Landlord and Tenant Act 1985, where you will need to:

  • Explain why the consultation process was not followed
  • Demonstrate that leaseholders have not been prejudiced as a result

Common reasons for dispensation include:

  • Emergency works that could not be delayed
  • Mistakes made during the consultation process

The key question the tribunal will consider is whether leaseholders have suffered any real disadvantage due to the lack of consultation.

The total cost of the application and hearing is £341. The application form and intructions for submission can be found here: https://www.gov.uk/government/publications/form-leasehold-5-application-for-the-dispensation-of-all-or-any-of-the-consultation-requirements-provided-for-by-section-20-of-the-landlord-and-tenan

What types of works are covered?

Section 20 applies to:

  • Major repairs and maintenance
  • Improvements (depending on lease wording)
  • Long-term service contracts

It does not apply to routine, low-cost maintenance where the thresholds are not exceeded.

What happens if initial estimates are under the qualifying amount but later exceed it?

If costs increase and exceed the thresholds:

  • You may need to start the consultation process
  • If works are already underway, you may need to:
  • Seek retrospective dispensation

As a rule of thumb, if there is any risk of exceeding the threshold, it is safer to consult from the outset.

Common mistakes to avoid

Some of the most common pitfalls include:

  • Starting works before the consultation process is complete
  • Not allowing the full 30-day consultation periods
  • Failing to properly consider or respond to leaseholder observations
  • Not including all required information in notices
  • Failing to obtain estimates in line with the statutory requirements

Avoiding these mistakes can save significant time, cost, and potential disputes.

How can Flatwise help?

We allow users to easily manage the Section 20 schedules, with templates that are compliant with Section 20 legislation and an easy-to-follow workflow, all included in the price of subscription (unlike managing agents who will often charge between £150-£500 on top of their basic fees!).

What we provide:

  • Step-by-step guidance through each notice
  • Automatically generated, compliant templates
  • Built-in timelines to ensure deadlines are not missed
  • Tools to help you keep a clear audit trail of how and when notices are served
  • Centralised communication with leaseholders, including managing observations and contractor nominations

Section 20 doesn’t have to be confusing — with the right tools and structure, it can be a straightforward and transparent process.

Get started for free

Topics: Section 20, RTM, RMC, Landlord and Tenant Act 1985, Service charges, Leaseholder consultation, Major works, Long-term agreements, First-tier Tribunal, Dispensation

Updated: