What is a section 20 notice?
· 7 min read
What a section 20 notice is, when you need one, what it must say, and what happens if it's skipped.
tl;dr: A section 20 notice is a formal letter that whoever collects your building's service charge must send every leaseholder before starting works that would cost any one of them more than £250, or signing a contract of over 12 months that would cost any one of them more than £100 a year. If the consultation isn't done properly, each leaseholder's share is capped at £250 (or £100 a year) unless a tribunal agrees to waive the requirements. Most major works need up to three notices, and the first two each give leaseholders 30 days to respond.
The name comes from section 20 of the Landlord and Tenant Act 1985; what the notices must say is set by the 2003 consultation regulations. This guide covers England.
When is a section 20 notice required?
You need one whenever any single leaseholder's share of a job would be more than £250, or their share of a long-term contract would be more than £100 in a year. It's the largest share that counts, not the average.
That catches more jobs than people expect:
- Qualifying works: roof repairs, external redecoration, a new door entry system, fire safety works.
- Qualifying long-term agreements: contracts of more than 12 months, such as cleaning, gardening or lift maintenance.
A worked example
A building has 12 flats. The leases split costs by size, and the largest flat pays 10%.
- A £2,400 repair costs that flat £240. No consultation needed.
- A £3,000 repair costs that flat £300. Section 20 applies, even though an equal split would have been exactly £250 each.
To find your own trigger point, divide £250 by the largest share. Here that's £250 ÷ 10% = £2,500. Any job above that needs consultation. Work it out on the full cost the company will pay, including any VAT.
Who has to send a section 20 notice?
The law says "the landlord", but that includes whoever has the right to collect the service charge. If your building has taken over management through the Right to Manage, the RTM company takes on the duty. If a residents' management company runs the building, it's that company.
In practice it falls to the directors: it's one of the core Right to Manage company directors' responsibilities. Notices go to every leaseholder, and to any recognised tenants' association.
What are the three section 20 notices?
For most major works there are three stages:
- Notice of intention. Tells leaseholders what you plan to do and why, and invites their comments and suggested contractors.
- Statement of estimates. Shares at least two quotes and invites comments again.
- Notice of reasons. Explains why you picked the contractor. Only needed if you didn't choose the cheapest quote or a contractor a leaseholder nominated.
Long-term agreements follow a similar pattern. Work under a long-term agreement that has already been consulted on needs only a notice of intention. For the full step-by-step, see our guide to the section 20 process.
What must a section 20 notice of intention include?
The first notice must be in writing and must:
- describe the works in general terms, or say where and when a description can be seen;
- explain why you think the works are necessary;
- invite leaseholders to send written observations, giving the address and the date the 30 days end;
- invite each leaseholder to nominate a contractor you should try to get a quote from.
Keep a dated copy of every notice and a note of how and when it was sent. Serve it the way your lease says notices must be served. If a dispute ever reaches a tribunal, that record is your evidence.
What is the time limit on a section 20 notice?
Each of the first two notices gives leaseholders 30 days, starting on the date of the notice, to respond. If you need a notice of reasons, it must go out within 21 days of signing the contract.
So a straightforward consultation takes at least two months, and usually longer once you allow time to collect quotes. Start as soon as you know the work is coming.
How does section 20 protect leaseholders?
It gives everyone paying for the works a say before the money is committed:
- They're told what's planned and why, and can comment.
- They can nominate a contractor, and you must try to get a quote from them.
- They see the quotes. At least one must come from someone wholly unconnected with the company. A contractor who is a director, or a close relative of one, counts as connected.
- You must take their comments into account, and explain your choice if you don't pick the cheapest or nominated quote.
For resident-run buildings this also protects the directors. A clean consultation is the best answer to a neighbour who later questions a bill.
What happens if a leaseholder refuses to pay?
If you consulted properly, the costs were reasonably incurred, the work is of a reasonable standard and the lease allows the charge, the leaseholder still owes their share. Refusing to pay doesn't cancel the debt. Either side can ask the First-tier Tribunal (Property Chamber) to decide whether the charge is payable and reasonable.
If you didn't consult, or got a step wrong, you can only recover £250 per leaseholder for the works (or £100 a year for a long-term agreement), unless the tribunal grants dispensation. For a practical approach to chasing a neighbour who is behind, see our guide to service charge arrears.
Can you skip section 20 in an emergency?
You can do urgent work first, such as a collapsed ceiling or a dangerous roof, and then apply to the tribunal for dispensation under section 20ZA. The tribunal can dispense with the requirements if it's reasonable to do so. You can also apply before the work starts if you know you can't consult in time.
Since the Supreme Court's decision in Daejan Investments Ltd v Benson [2013] UKSC 14, the key question is whether leaseholders were actually prejudiced by the missing consultation. The tribunal can attach conditions, such as paying the leaseholders' reasonable costs. Applications use form Leasehold 5 on GOV.UK, and a tribunal fee applies.
Is a section 20B notice the same thing?
No. A section 20B notice is about timing, not consultation. Under section 20B, you generally can't charge for costs incurred more than 18 months before you send the demand, unless you warned leaseholders in writing within those 18 months that the costs had been incurred and they'd have to contribute.
The Leasehold and Freehold Reform Act 2024 replaces that warning with a "future demand notice" in a form set by regulations. That change takes effect in England on 1 April 2027 under SI 2026/1128. If your building has costs that won't be billed for a while, check the new form before then.
How Flatwise can help
The hard part of section 20 for volunteer directors isn't understanding it. It's getting every notice, date and quote right while holding down a day job.
Flatwise flags a repair as needing section 20 when its estimate would push the largest share over £250. It then walks you through each notice in order, enforces the 30-day periods, and creates a personalised notice for every leaseholder, with a record of what was sent. It's included when you run your building on Flatwise.